850MW Ratle new joint venture project to become reality soon
Lt Governor takes a comprehensive review of the various NHPC projects in J&K
Modalities for expediting the upcoming Pakal Dul, Kiru, Kwar projects finalized
• Issues directions for ensuring completion of ongoing projects within set timelines
• Calls for better synergy between agencies for making J&K power surplus


SRINAGAR, OCTOBER 11: Lieutenant Governor, Manoj Sinha took a comprehensive review of the status of various projects of National Hydroelectric Power Corporation (NHPC) in the Union Territory of Jammu and Kashmir in a meeting at the Raj Bhavan here today.
With the intervention of Lt Governor, modalities have been finalized for the upcoming 850MW, new joint venture Ratle project which will augment the existing generation capacity in the region. The meeting also decided that the supplementary MOU will be finalized through joint discussions between MOP(GOI), GoJK (JKSPDC) and NHPC.
Threadbare discussions were also held to fast-track the execution of the upcoming Pakal Dul, Kiru, and Kwar projects. Cumulatively, the upcoming power projects will generate 6298MW at the cost of Rs 54593 crores substantially enhancing the generation capacity in the region.
Chairman & Managing Director (CMD), NHPC Limited, AK Singh briefed the Lt Governor regarding the details of commissioned and generation capacity of NHPC’s Power Stations across J&K, besides the present status of the NHPC projects under execution in the UT.
The Lieutenant Governor was briefed about the completed Projects of NHPC in J&K and their generation capacity included – Power Stations- Salal (Stage I & II), MW 690 ; URI-I , MW 480; Dulhasti- MW 390; Sewa II, MW 120; Uri II, MW, 240 and Kishanganga, MW 330; collectively generating 2250 MW.
The Lt Governor issued on-spot directions for completion of ongoing projects and called for better synergy between agencies for making J&K a power surplus region in the country. Remove bottlenecks, if any, hampering the completion of the projects, he added.
Stressing on speedy completion of the projects, the Lt Governor directed the concerned officers for completion of all projects within the set timelines. He also asked the NHPC functionaries to take innovative measures and explore various conventional and non-conventional sources for the development of hydropower sector in Jammu and Kashmir.
The Lt Governor enquired about the CSR works being carried out by the NHPC in the field of Healthcare, Education, Swachh Bharat and Vocational Training. He also sought details of the Direct & Indirect Employment generated through NHPC projects to residents of J&K.
It was also informed that NHPC has played a significant role in Rural Electrification in 5 Districts – Kathua, Udhampur, Jammu, Srinagar, and Budgam.
Sh. BVR Subrahmanyam, Chief Secretary; Sh. Rohit Kansal, Principal Secretary, Power Development Department; Sh. AK Singh, CMD, NHPC; Sh. V K Maini, Executive Director, NHPC; Sh. Deepak Saigal, GM, Nodal Officer, Ratle; Sh. A.K. Choudhary, Managing Director, Chenab Valley Power Projects (CVPPL) and other senior functionaries of NHPC, PDD and CVPPL attended the meeting.

Related posts

Over 21,000 dogs to be sterilized in Srinagar within 16 months; No rabies detected, says SMC MVO ‘2023 survey using Peterson-Lincoln Method estimates 64,000 stray dogs in city’

Kashmir Indepth

Massive crowd gathers at Sonmarg as PM Narendra Modi set to address after Inaugurating Z-Morh Tunnel

Kashmir Indepth

CM Omar Abdullah Condemns Killing of Ashok Chouhan by “terrorists” in South Kashmir

Kashmir Indepth

Maha Navami celebrated with devotion in Kashmir

Zainab Hamdani

Covid-19: Allow us to resume bus services, Transporters to Govt

Kashmir Indepth

World SnowShoe Championship 2019: Laigroo to lead Kashmir SnowShoe athletes in Italy

Kashmir Indepth

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy